AFCON 2027: Will Kasarani Stadium be ready by the end of December?
The countdown is on for Kasarani Stadium, one of the venues selected by Kenya for AFCON 2027. The stadium, located at the Moi International Sports Centre and capable of holding 48,000 spectators, must be ready before December 31, 2026.
However, work is still ongoing. Images published on November 19 show workers improving the pitch and installing the skyboxes. The tournament will be hosted by Kenya, Uganda and Tanzania from June 19 to July 17, 2027.
CAF wants stadiums ready from January
The December 31 deadline is important for the organizers. CAF wants the stadiums and competition-related facilities to be operational from January 2027. During its inspection in February 2026, the governing body had concluded that none of the stadiums proposed by the three host countries yet met all its requirements. Kasarani was therefore due to undergo several upgrades.
CAF made another visit to the region in August. In September, its president, Patrice Motsepe, reiterated that the venues had to start hosting test matches from January 2027. He specifically called for work at Kasarani to be accelerated.
Pitch, lighting and skyboxes among the planned upgrades
The stadium renovation covers several areas. The work includes the pitch, drainage, irrigation, lighting, media areas and security facilities. According to project officials, the natural grass had reached around 70% germination during a recent Senate visit. It is to be reinforced with a hybrid system.
The drainage system is designed to clear water within three minutes. The lighting must also be upgraded to reach 3,000 lux, in line with CAF requirements. The project also includes 18 skyboxes, as well as VIP and commercial areas. Supporter access and facilities for people with disabilities are also part of the work.
Delays and safety concerns reported
Despite the progress reported, the project is still causing concern. During a recent inspection, senators raised issues including delays, accessibility difficulties, fire safety and emergency preparedness. The project team explained that payment difficulties had contributed to the delays. It says the contractor has increased the number of workers to speed up the work.
Nicholas Musonye, chairman of the local organizing committee for the AFCON, remains confident about the schedule. “By the end of December, we should be able to hand over all these facilities,” he said. With just weeks to go before the deadline, work continues at the 48,000-seat venue. Kenya must now complete the renovations and meet CAF requirements.